Method statement for The Unloading of Trussed Rafters
1. Trussed with a span not exceeding 3 metres:
Trusses in this category may be safely unloaded manually in accordance with the Trussed Rafter Association Handbook, provided, they are easily accessible on the lorry delivering them.
Putting our customers first
2. Trusses with a Span Of 3 Metres Or More:
2.1 Mechanical Offloading
We recommend mechanical offloading as the safest offloading method.
Trussed rafters should be unloaded by forklift truck, sideloader or crane wherever possible. The drivers of these vehicles should be trained in accordance with the C.I.T.B guidelines.
The area where the lorry delivering the trusses is to be unloaded should be a level clear safe area both for the delivery lorry and for the mechanical offloading equipment and should be free from overhead cabling to a height of 5.5 metres.
If in the process of unloading you assist the driver by removing and replacing customers trussed rafters, these must be carried out in compliance with the Road Vehicle Construction and use Regulations dated May 1993.
8 Major Centres throughout the UK and Ireland
2.2 Manual Offloading
This method should only be used if mechanical offloading is not possible. Persons involved in manual handling should be referred to the T.R.A Handbook, which details the correct procedures for handling storage and erection.
All manual handling must be carried out in accordance with the Manual Handling Regulations 1992.
Lorry Drivers may assist with the unloading either directly or in an advisory capacity, only if requested to do so by a representative of the customers company, who will then assume all responsibility for the drivers health and safety.
Drivers supervising a manual handling offload should satisfy themselves that there are a sufficient number of personnel allocated to process, by the customers company, to ensure that the offload is carried out as safely as possible.
|